{"id":2795,"date":"2021-08-11T19:56:05","date_gmt":"2021-08-11T19:56:05","guid":{"rendered":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/?p=2795"},"modified":"2021-08-11T19:56:05","modified_gmt":"2021-08-11T19:56:05","slug":"cash-flow-forecasting-in-cost-management","status":"publish","type":"post","link":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/2021\/08\/11\/cash-flow-forecasting-in-cost-management\/","title":{"rendered":"Cash Flow Forecasting In Cost Management"},"content":{"rendered":"<h1>Cash Flow Forecasting<\/h1>\n<p>With the latest Cost Management release, teams can now create forecast distributions for each budget item and access a project-level cash flow analysis to visualize the difference between planned actual and forecast quickly. <a href=\"https:\/\/workflows.construction.autodesk.com\/chapters\/cost-cash-flow-forecasting-bim-360\/\">Click here to view a step-by-step guide<\/a>.<\/p>\n<h2><strong>Connecting Cost &amp; Time<\/strong><\/h2>\n<ul>\n<li>Connect schedule tasks to budget line items to quickly determine duration and enable calculations for annual price increases.<\/li>\n<\/ul>\n<div style=\"width: 640px;\" class=\"wp-video\"><video class=\"wp-video-shortcode\" id=\"video-2795-1\" width=\"640\" height=\"348\" loop autoplay preload=\"auto\" controls=\"controls\"><source type=\"video\/mp4\" src=\"https:\/\/blogs.autodesk.com\/bim360-release-notes\/wp-content\/uploads\/sites\/127\/2021\/08\/11\/Cost-Cashflow-Forecasting-1-final.mp4?_=1\" \/><a href=\"https:\/\/blogs.autodesk.com\/bim360-release-notes\/wp-content\/uploads\/sites\/127\/2021\/08\/11\/Cost-Cashflow-Forecasting-1-final.mp4\">https:\/\/blogs.autodesk.com\/bim360-release-notes\/wp-content\/uploads\/sites\/127\/2021\/08\/11\/Cost-Cashflow-Forecasting-1-final.mp4<\/a><\/video><\/div>\n<h2><\/h2>\n<p>&nbsp;<\/p>\n<h2><b><b>Built-In Forecast Distribution Curves<\/b><\/b><\/h2>\n<ul>\n<li>Perform\u00a0forecast distributions for each budget line item. Choose from f<span style=\"font-weight: 400\">o<\/span><b><b><b><span style=\"font-weight: 400\">ur built-in forecast distribution curves, including front-loaded, rear-loaded, typical, and linear. <\/span><\/b><\/b><\/b><\/li>\n<li><b><b><b><span style=\"font-weight: 400\">When performing distributions to items connected to schedule tasks, dates automatically pull in, but can be altered if necessary. <\/span><\/b><\/b><\/b><\/li>\n<li><b><b><b><span style=\"font-weight: 400\">Customize the distribution further by adding or removing date ranges. <\/span><\/b><\/b><\/b><\/li>\n<li><b><b><b><span style=\"font-weight: 400\">Easily make edits within the forecast final cost field as you make projections. <\/span><\/b><\/b><\/b><\/li>\n<li><b><b><b><span style=\"font-weight: 400\">The system will auto-flag if the distribution total doesn\u2019t match the forecast-final cost.<br \/>\n<\/span><\/b><\/b><\/b><b><b><\/b><\/b><\/li>\n<\/ul>\n<div style=\"width: 640px;\" class=\"wp-video\"><video class=\"wp-video-shortcode\" id=\"video-2795-2\" width=\"640\" height=\"349\" loop autoplay preload=\"auto\" controls=\"controls\"><source type=\"video\/mp4\" src=\"https:\/\/blogs.autodesk.com\/bim360-release-notes\/wp-content\/uploads\/sites\/127\/2021\/08\/11\/Cost-Cashflow-Forecasting-2.mp4?_=2\" \/><a href=\"https:\/\/blogs.autodesk.com\/bim360-release-notes\/wp-content\/uploads\/sites\/127\/2021\/08\/11\/Cost-Cashflow-Forecasting-2.mp4\">https:\/\/blogs.autodesk.com\/bim360-release-notes\/wp-content\/uploads\/sites\/127\/2021\/08\/11\/Cost-Cashflow-Forecasting-2.mp4<\/a><\/video><\/div>\n<h2><\/h2>\n<p>&nbsp;<\/p>\n<h2><b>Project Level Cash Flow Analysis<\/b><\/h2>\n<ul>\n<li><span style=\"font-weight: 400\">Access a project-level cash flow analysis in the new Forecast tool.\u00a0A built-in dynamic time-versus-money chart, allows you to visualize the project-level cash flow distribution throughout the project lifecycle. <\/span><\/li>\n<li><span style=\"font-weight: 400\">Within this view, the information is summarized by revised budget, work completed, actual costs, and forecast-final cost, which can be viewed by period or cumulatively. <\/span><\/li>\n<li><span style=\"font-weight: 400\">Ability to quickly drill down into details if needed.\u00a0<\/span><\/li>\n<\/ul>\n<div style=\"width: 640px;\" class=\"wp-video\"><video class=\"wp-video-shortcode\" id=\"video-2795-3\" width=\"640\" height=\"347\" loop autoplay preload=\"auto\" controls=\"controls\"><source type=\"video\/mp4\" src=\"https:\/\/blogs.autodesk.com\/bim360-release-notes\/wp-content\/uploads\/sites\/127\/2021\/08\/11\/Cost-Cashflow-Forecasting-3.mp4?_=3\" \/><a href=\"https:\/\/blogs.autodesk.com\/bim360-release-notes\/wp-content\/uploads\/sites\/127\/2021\/08\/11\/Cost-Cashflow-Forecasting-3.mp4\">https:\/\/blogs.autodesk.com\/bim360-release-notes\/wp-content\/uploads\/sites\/127\/2021\/08\/11\/Cost-Cashflow-Forecasting-3.mp4<\/a><\/video><\/div>\n","protected":false},"excerpt":{"rendered":"<p>Cash Flow Forecasting<\/p>\n<p>With the latest Cost Management release, teams can now create forecast distributions for each budget item and access a project-level cash flow analysis to visualize the difference between planned actual and forecast quickly. <a href=\"https:\/\/workflows.construction.autodesk.com\/chapters\/cost-cash-flow-forecasting-bim-360\/\">Click here to view a step-by-step guide<\/a>.<\/p>\n<p>Connecting Cost &amp; <\/p>\n","protected":false},"author":22366,"featured_media":2799,"comment_status":"open","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"_acf_changed":false,"inline_featured_image":false,"footnotes":""},"categories":[81,18,82],"tags":[],"class_list":["post-2795","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-cost-management","category-next-gen-bim360","category-project-controls"],"acf":[],"yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v27.3 - https:\/\/yoast.com\/product\/yoast-seo-wordpress\/ -->\n<title>Cash Flow Forecasting In Cost Management - BIM 360 Release Notes<\/title>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/blogs.autodesk.com\/bim360-release-notes\/2021\/08\/11\/cash-flow-forecasting-in-cost-management\/\" \/>\n<meta property=\"og:locale\" content=\"en_US\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Cash Flow Forecasting In Cost Management - BIM 360 Release Notes\" \/>\n<meta property=\"og:description\" content=\"Cash Flow Forecasting With the latest Cost Management release, teams can now create forecast distributions for each budget item and access a project-level cash flow analysis to visualize the difference between planned actual and forecast quickly. Click here to view a step-by-step guide. Connecting Cost &amp;\" \/>\n<meta property=\"og:url\" content=\"https:\/\/blogs.autodesk.com\/bim360-release-notes\/2021\/08\/11\/cash-flow-forecasting-in-cost-management\/\" \/>\n<meta property=\"og:site_name\" content=\"BIM 360 Release Notes\" \/>\n<meta property=\"article:published_time\" content=\"2021-08-11T19:56:05+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/blogs.autodesk.com\/bim360-release-notes\/wp-content\/uploads\/sites\/127\/2021\/08\/11\/Cashflow-Forecasting.jpg\" \/>\n\t<meta property=\"og:image:width\" content=\"1920\" \/>\n\t<meta property=\"og:image:height\" content=\"1044\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/jpeg\" \/>\n<meta name=\"author\" content=\"Ian Turner\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:label1\" content=\"Written by\" \/>\n\t<meta name=\"twitter:data1\" content=\"Ian Turner\" \/>\n\t<meta name=\"twitter:label2\" content=\"Est. reading time\" \/>\n\t<meta name=\"twitter:data2\" content=\"2 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\\\/\\\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\\\/\\\/blogs.autodesk.com\\\/bim360-release-notes\\\/2021\\\/08\\\/11\\\/cash-flow-forecasting-in-cost-management\\\/#article\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/blogs.autodesk.com\\\/bim360-release-notes\\\/2021\\\/08\\\/11\\\/cash-flow-forecasting-in-cost-management\\\/\"},\"author\":{\"name\":\"Ian Turner\",\"@id\":\"https:\\\/\\\/blogs.autodesk.com\\\/bim360-release-notes\\\/#\\\/schema\\\/person\\\/f7ae60b470148ba8999768d7aa89b9ca\"},\"headline\":\"Cash Flow Forecasting In Cost Management\",\"datePublished\":\"2021-08-11T19:56:05+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\\\/\\\/blogs.autodesk.com\\\/bim360-release-notes\\\/2021\\\/08\\\/11\\\/cash-flow-forecasting-in-cost-management\\\/\"},\"wordCount\":290,\"commentCount\":0,\"image\":{\"@id\":\"https:\\\/\\\/blogs.autodesk.com\\\/bim360-release-notes\\\/2021\\\/08\\\/11\\\/cash-flow-forecasting-in-cost-management\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/blogs.autodesk.com\\\/bim360-release-notes\\\/wp-content\\\/uploads\\\/sites\\\/127\\\/2021\\\/08\\\/11\\\/Cashflow-Forecasting.jpg\",\"articleSection\":[\"Cost Management\",\"Next Gen BIM 360\",\"Project Controls\"],\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"CommentAction\",\"name\":\"Comment\",\"target\":[\"https:\\\/\\\/blogs.autodesk.com\\\/bim360-release-notes\\\/2021\\\/08\\\/11\\\/cash-flow-forecasting-in-cost-management\\\/#respond\"]}]},{\"@type\":\"WebPage\",\"@id\":\"https:\\\/\\\/blogs.autodesk.com\\\/bim360-release-notes\\\/2021\\\/08\\\/11\\\/cash-flow-forecasting-in-cost-management\\\/\",\"url\":\"https:\\\/\\\/blogs.autodesk.com\\\/bim360-release-notes\\\/2021\\\/08\\\/11\\\/cash-flow-forecasting-in-cost-management\\\/\",\"name\":\"Cash Flow Forecasting In Cost Management - BIM 360 Release Notes\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/blogs.autodesk.com\\\/bim360-release-notes\\\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\\\/\\\/blogs.autodesk.com\\\/bim360-release-notes\\\/2021\\\/08\\\/11\\\/cash-flow-forecasting-in-cost-management\\\/#primaryimage\"},\"image\":{\"@id\":\"https:\\\/\\\/blogs.autodesk.com\\\/bim360-release-notes\\\/2021\\\/08\\\/11\\\/cash-flow-forecasting-in-cost-management\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/blogs.autodesk.com\\\/bim360-release-notes\\\/wp-content\\\/uploads\\\/sites\\\/127\\\/2021\\\/08\\\/11\\\/Cashflow-Forecasting.jpg\",\"datePublished\":\"2021-08-11T19:56:05+00:00\",\"author\":{\"@id\":\"https:\\\/\\\/blogs.autodesk.com\\\/bim360-release-notes\\\/#\\\/schema\\\/person\\\/f7ae60b470148ba8999768d7aa89b9ca\"},\"breadcrumb\":{\"@id\":\"https:\\\/\\\/blogs.autodesk.com\\\/bim360-release-notes\\\/2021\\\/08\\\/11\\\/cash-flow-forecasting-in-cost-management\\\/#breadcrumb\"},\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\\\/\\\/blogs.autodesk.com\\\/bim360-release-notes\\\/2021\\\/08\\\/11\\\/cash-flow-forecasting-in-cost-management\\\/\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/blogs.autodesk.com\\\/bim360-release-notes\\\/2021\\\/08\\\/11\\\/cash-flow-forecasting-in-cost-management\\\/#primaryimage\",\"url\":\"https:\\\/\\\/blogs.autodesk.com\\\/bim360-release-notes\\\/wp-content\\\/uploads\\\/sites\\\/127\\\/2021\\\/08\\\/11\\\/Cashflow-Forecasting.jpg\",\"contentUrl\":\"https:\\\/\\\/blogs.autodesk.com\\\/bim360-release-notes\\\/wp-content\\\/uploads\\\/sites\\\/127\\\/2021\\\/08\\\/11\\\/Cashflow-Forecasting.jpg\",\"width\":1920,\"height\":1044},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\\\/\\\/blogs.autodesk.com\\\/bim360-release-notes\\\/2021\\\/08\\\/11\\\/cash-flow-forecasting-in-cost-management\\\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\\\/\\\/blogs.autodesk.com\\\/bim360-release-notes\\\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Cash Flow Forecasting In Cost Management\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\\\/\\\/blogs.autodesk.com\\\/bim360-release-notes\\\/#website\",\"url\":\"https:\\\/\\\/blogs.autodesk.com\\\/bim360-release-notes\\\/\",\"name\":\"BIM 360 Release Notes\",\"description\":\"Updates and enhancements\",\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\\\/\\\/blogs.autodesk.com\\\/bim360-release-notes\\\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en-US\"},{\"@type\":\"Person\",\"@id\":\"https:\\\/\\\/blogs.autodesk.com\\\/bim360-release-notes\\\/#\\\/schema\\\/person\\\/f7ae60b470148ba8999768d7aa89b9ca\",\"name\":\"Ian Turner\",\"image\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/blogs.autodesk.com\\\/bim360-release-notes\\\/wp-content\\\/uploads\\\/sites\\\/127\\\/2018\\\/11\\\/1FDAD67D-BC16-477F-A05C-F5463A8B2ACD-150x150.jpeg\",\"url\":\"https:\\\/\\\/blogs.autodesk.com\\\/bim360-release-notes\\\/wp-content\\\/uploads\\\/sites\\\/127\\\/2018\\\/11\\\/1FDAD67D-BC16-477F-A05C-F5463A8B2ACD-150x150.jpeg\",\"contentUrl\":\"https:\\\/\\\/blogs.autodesk.com\\\/bim360-release-notes\\\/wp-content\\\/uploads\\\/sites\\\/127\\\/2018\\\/11\\\/1FDAD67D-BC16-477F-A05C-F5463A8B2ACD-150x150.jpeg\",\"caption\":\"Ian Turner\"},\"url\":\"https:\\\/\\\/blogs.autodesk.com\\\/bim360-release-notes\\\/author\\\/ianturner\\\/\"}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"Cash Flow Forecasting In Cost Management - BIM 360 Release Notes","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/2021\/08\/11\/cash-flow-forecasting-in-cost-management\/","og_locale":"en_US","og_type":"article","og_title":"Cash Flow Forecasting In Cost Management - BIM 360 Release Notes","og_description":"Cash Flow Forecasting With the latest Cost Management release, teams can now create forecast distributions for each budget item and access a project-level cash flow analysis to visualize the difference between planned actual and forecast quickly. Click here to view a step-by-step guide. Connecting Cost &amp;","og_url":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/2021\/08\/11\/cash-flow-forecasting-in-cost-management\/","og_site_name":"BIM 360 Release Notes","article_published_time":"2021-08-11T19:56:05+00:00","og_image":[{"width":1920,"height":1044,"url":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/wp-content\/uploads\/sites\/127\/2021\/08\/11\/Cashflow-Forecasting.jpg","type":"image\/jpeg"}],"author":"Ian Turner","twitter_card":"summary_large_image","twitter_misc":{"Written by":"Ian Turner","Est. reading time":"2 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/2021\/08\/11\/cash-flow-forecasting-in-cost-management\/#article","isPartOf":{"@id":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/2021\/08\/11\/cash-flow-forecasting-in-cost-management\/"},"author":{"name":"Ian Turner","@id":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/#\/schema\/person\/f7ae60b470148ba8999768d7aa89b9ca"},"headline":"Cash Flow Forecasting In Cost Management","datePublished":"2021-08-11T19:56:05+00:00","mainEntityOfPage":{"@id":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/2021\/08\/11\/cash-flow-forecasting-in-cost-management\/"},"wordCount":290,"commentCount":0,"image":{"@id":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/2021\/08\/11\/cash-flow-forecasting-in-cost-management\/#primaryimage"},"thumbnailUrl":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/wp-content\/uploads\/sites\/127\/2021\/08\/11\/Cashflow-Forecasting.jpg","articleSection":["Cost Management","Next Gen BIM 360","Project Controls"],"inLanguage":"en-US","potentialAction":[{"@type":"CommentAction","name":"Comment","target":["https:\/\/blogs.autodesk.com\/bim360-release-notes\/2021\/08\/11\/cash-flow-forecasting-in-cost-management\/#respond"]}]},{"@type":"WebPage","@id":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/2021\/08\/11\/cash-flow-forecasting-in-cost-management\/","url":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/2021\/08\/11\/cash-flow-forecasting-in-cost-management\/","name":"Cash Flow Forecasting In Cost Management - BIM 360 Release Notes","isPartOf":{"@id":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/#website"},"primaryImageOfPage":{"@id":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/2021\/08\/11\/cash-flow-forecasting-in-cost-management\/#primaryimage"},"image":{"@id":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/2021\/08\/11\/cash-flow-forecasting-in-cost-management\/#primaryimage"},"thumbnailUrl":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/wp-content\/uploads\/sites\/127\/2021\/08\/11\/Cashflow-Forecasting.jpg","datePublished":"2021-08-11T19:56:05+00:00","author":{"@id":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/#\/schema\/person\/f7ae60b470148ba8999768d7aa89b9ca"},"breadcrumb":{"@id":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/2021\/08\/11\/cash-flow-forecasting-in-cost-management\/#breadcrumb"},"inLanguage":"en-US","potentialAction":[{"@type":"ReadAction","target":["https:\/\/blogs.autodesk.com\/bim360-release-notes\/2021\/08\/11\/cash-flow-forecasting-in-cost-management\/"]}]},{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/2021\/08\/11\/cash-flow-forecasting-in-cost-management\/#primaryimage","url":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/wp-content\/uploads\/sites\/127\/2021\/08\/11\/Cashflow-Forecasting.jpg","contentUrl":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/wp-content\/uploads\/sites\/127\/2021\/08\/11\/Cashflow-Forecasting.jpg","width":1920,"height":1044},{"@type":"BreadcrumbList","@id":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/2021\/08\/11\/cash-flow-forecasting-in-cost-management\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/"},{"@type":"ListItem","position":2,"name":"Cash Flow Forecasting In Cost Management"}]},{"@type":"WebSite","@id":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/#website","url":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/","name":"BIM 360 Release Notes","description":"Updates and enhancements","potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en-US"},{"@type":"Person","@id":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/#\/schema\/person\/f7ae60b470148ba8999768d7aa89b9ca","name":"Ian Turner","image":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/wp-content\/uploads\/sites\/127\/2018\/11\/1FDAD67D-BC16-477F-A05C-F5463A8B2ACD-150x150.jpeg","url":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/wp-content\/uploads\/sites\/127\/2018\/11\/1FDAD67D-BC16-477F-A05C-F5463A8B2ACD-150x150.jpeg","contentUrl":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/wp-content\/uploads\/sites\/127\/2018\/11\/1FDAD67D-BC16-477F-A05C-F5463A8B2ACD-150x150.jpeg","caption":"Ian Turner"},"url":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/author\/ianturner\/"}]}},"_links":{"self":[{"href":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/wp-json\/wp\/v2\/posts\/2795","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/wp-json\/wp\/v2\/users\/22366"}],"replies":[{"embeddable":true,"href":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/wp-json\/wp\/v2\/comments?post=2795"}],"version-history":[{"count":0,"href":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/wp-json\/wp\/v2\/posts\/2795\/revisions"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/wp-json\/wp\/v2\/media\/2799"}],"wp:attachment":[{"href":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/wp-json\/wp\/v2\/media?parent=2795"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/wp-json\/wp\/v2\/categories?post=2795"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/blogs.autodesk.com\/bim360-release-notes\/wp-json\/wp\/v2\/tags?post=2795"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}